Project management often requires juggling various tasks, schedules, and budgets while keeping stakeholders informed of progress. Among the many tools and metrics available to project managers, Planned Value (PV), Earned Value (EV), Actual Cost (AC), and Cost Performance Index (CPI) stand out as critical indicators for evaluating a project’s performance and health. These metrics are part of Earned Value Management (EVM), a systematic approach to project performance measurement and control. In this blog post, we’ll delve into how to calculate these metrics and explore why they are essential for successful project management.


 

Understanding the Metrics

Planned Value (PV)

Planned Value, also known as Budgeted Cost of Work Scheduled (BCWS), is the authorized budget assigned to scheduled work. It represents the value of work that should have been completed according to the project plan at a specific point in time.

Understanding the Metrics

Planned Value, also known as Budgeted Cost of Work Scheduled (BCWS), is the authorized budget assigned to scheduled work. It represents the value of work that should have been completed according to the project plan at a specific point in time.

For example, if the total project budget is $100,000 and by week 4 you planned to complete 25% of the project, then:

Earned Value, also referred to as Budgeted Cost of Work Performed (BCWP), measures the value of work actually completed at a given point in time, expressed in terms of the budget.

For instance, if by week 4, 20% of the project work has been completed on a project with a $100,000 budget:

Actual Cost, or Actual Cost of Work Performed (ACWP), is the total cost incurred for the work completed at a specific point in time. This value is obtained from financial systems tracking the actual expenses.

If by week 4, your project has incurred $22,000 in costs, then AC is $22,000.

CPI is a measure of cost efficiency and is calculated as the ratio of Earned Value to Actual Cost. It shows how well the project is sticking to its budget.

If the Earned Value (EV) is $20,000 and the Actual Cost (AC) is $22,000:

A CPI value of less than 1 indicates that the project is over budget, while a value greater than 1 shows the project is under budget.

How to Calculate the Metrics Step by Step

  • Determine Total Project Budget: Begin by identifying the total budget allocated for the project.

  • Establish Planned Percentage Completion (Planned % Complete): Review your project schedule to determine the percentage of work planned to be completed at the current time.

  • Calculate PV: Use the Planned % Complete and multiply it by the total budget.

  • Measure Actual Work Completed (Actual % Complete): Conduct a review of the work done so far to determine the percentage of work actually completed.

  • Calculate EV: Multiply Actual % Complete by the total budget.

  • Gather Actual Costs (AC): Refer to your financial records or project management software to sum up the costs incurred so far.

  • Compute CPI: Divide EV by AC to assess cost efficiency.

,Example Scenario

Imagine a software development project with the following details:

  • Total Budget: $200,000

  • Planned Completion: 50%

  • Actual Completion: 45%

  • Actual Costs to Date: $120,000

  • Planned Value (PV): $100000

  • Earned Value (EV): $90,000

  • Actual Cost (AC): AC = $120,000 (from financial records).

  • Cost Performance Index (CPI): <1

This CPI indicates that the project is currently over budget, as the value of work completed ($90,000) is less than the actual cost incurred ($120,000).

Tracking Progress Against the Plan

PV, EV, and AC provide a clear picture of how a project is progressing compared to its planned schedule and budget. By evaluating these metrics regularly, project managers can identify delays or budget overruns early and take corrective action.

Cost Efficiency Analysis

CPI is a powerful metric for understanding cost efficiency. A CPI less than 1 signals that a project is spending more than planned for the work completed, while a CPI greater than 1 indicates cost savings. This insight allows project managers to adjust resource allocation and control expenses more effectively.

Forecasting Future Performance

EVM metrics enable accurate forecasting of the project’s total cost and timeline. For instance:

  • Estimate at Completion (EAC):

    Using the example above:

    This indicates the project will likely cost $266,667 to complete if current trends continue.

  • Estimate to Complete (ETC):

     

    This shows that an additional $146,667 will be required to finish the project.

Objective Performance Evaluation

By relying on quantitative metrics like EV, PV, and CPI, project managers can provide objective and data-driven performance updates to stakeholders. This builds trust and ensures transparency.

Improved Decision-Making

With accurate metrics, project managers can make informed decisions about resource allocation, scope adjustments, and schedule modifications to bring a project back on track.

Types of Contracts in Project Management

Selecting the Right Contract Type In project management, selecting the right type of contract is crucial for aligning expectations, managing risk, and ensuring smooth collaboration between buyers and sellers. Different types of contracts determine how costs are...

Cause and Effect Diagram in Project Management

When I first started managing projects, I used to think every problem had a clear and obvious solution. If a deployment failed, it was probably the code. If a team was behind schedule, they were likely just overcommitted. But the more projects I managed, the more I...

Estimated project hours and critical path impact

When managing a project, understanding two key metrics—total estimated hours and critical path hours—is essential for accurate financial forecasting and timeline estimation. These two data points influence everything from resource allocation to profitability. In this...

Project Timelines and Budgets – A Beginner’s Guide

When managing a project, two of the most critical elements to monitor closely are Project Timelines and Budgets. While they may seem like separate metrics, they’re deeply connected—and a change in one almost always affects the other. The Cost of Delays Every day a...

RICE Scoring to Prioritize Projects

As a project manager, I constantly face the challenge of deciding which initiatives deserve priority. With limited time and resources, making the right choices is crucial. That’s where RICE Scoring comes into play. It’s my go-to framework for making objective,...

Mastering IT Development Timeline Estimation

Mastering IT Development Timeline Estimation and determining a realistic target end date are crucial for successful project management. Many projects suffer from delays due to inaccurate estimations, leading to budget overruns, missed deadlines, and stakeholder...

How to Conduct a Successful Project Meeting & Engage Stakeholders Effectively

As a project manager, conducting a meeting is more than just gathering people in a room to discuss tasks; it’s about steering the project in the right direction, ensuring alignment, and addressing concerns before they become roadblocks. From the moment I step into a...

Project Manager Skills Needed in Your First PM Role

Stepping into your first role as a Project Manager (PM) can be both exciting and daunting. While you may have a solid theoretical understanding of project management, the real-world application of PM skills requires a unique blend of technical knowledge, leadership,...

Estimating project end dates in the initiation phase

Estimating the end date of a project during the initiation phase is one of the most challenging tasks in project management. At this early stage, there are too many unknowns, making it difficult to provide an accurate timeline. Many factors contribute to the...

Breaking Into Project Management

How I Broke Into Project Management (And How You Can Too) Breaking into project management was one of the best career moves I ever made, but it wasn’t something that happened overnight. Like many people, I didn’t start my career with a project management title, but I...

Common Challenges and Tips

While PV, EV, AC, and CPI are invaluable metrics, project managers may encounter challenges when using them. Below are some common issues and tips to address them:

  • Challenge: Inaccurate Data Collection

    • Tip: Use reliable project management tools and financial systems to track progress and costs accurately.

  • Challenge: Misestimating Planned and Actual Percentages

    • Tip: Conduct regular reviews and involve team members to get accurate estimates of work completed.

  • Challenge: Overcomplicating the Process

    • Tip: Simplify calculations using project management software with built-in EVM features, such as Microsoft Project, Primavera P6, or Smartsheet.

  • Challenge: Lack of Stakeholder Understanding

    • Tip: Educate stakeholders about the importance of EVM metrics and how they reflect project performance.

Conclusion

Planned Value (PV), Earned Value (EV), Actual Cost (AC), and Cost Performance Index (CPI) are indispensable tools for effective project management. They provide a comprehensive view of a project’s performance in terms of cost and schedule, enabling managers to identify issues early, forecast future performance, and communicate progress effectively to stakeholders. By mastering these metrics and integrating them into your project management practices, you can ensure better control, improved decision-making, and ultimately, the success of your projects.